HI,

I was evaluating VSE88 with MA453. Deployed like 20 out 400 systems from the EVAL branch.

Now I am wondering about how to go to completely deploy to whole infrastructure.

Should I finalise the whole deployement (400 systems) from the EVAL branch and once that is done flip the MA update policy to CURRENT?

Would that be a good route to go?

Thanks

0 Kudos
1 Solution

Accepted Solutions
petersimmons
Level 12

Re: VSE migrations versus branch

Jump to solution

Just check VSE 8.8 into the Current branch. Unless there's an actual deployment task it won't 'accidentally' upgrade from 8.7 to 8.8. Plus 8.8 has been out a long time. If it were my system I'd just upgrade everyone. You can easily do several hundred automatically in a single afternoon.

0 Kudos
2 Replies
petersimmons
Level 12

Re: VSE migrations versus branch

Jump to solution

Just check VSE 8.8 into the Current branch. Unless there's an actual deployment task it won't 'accidentally' upgrade from 8.7 to 8.8. Plus 8.8 has been out a long time. If it were my system I'd just upgrade everyone. You can easily do several hundred automatically in a single afternoon.

0 Kudos

Re: VSE migrations versus branch

Jump to solution

Sounds fair enough.