Change schedule of virusscan 8.8

Jump to solution

Dear All,

My Versions :

- EPO 5.3.1

- Agent 5.0.2

- VirusScan 8.8

I don't find how to change the setting of the update VirusScan schedule in the EPO console.

In the clients, the default value is daily 17H.

Thanks in advance for your help.

Regards

Romain

1 Solution

Accepted Solutions
Highlighted

Re: Change schedule of virusscan 8.8

Jump to solution

When you create the McAfee Agent Product Update Task and assign it to the Client, during the Assign Client Task configuration at the Schedule stage (Stage 2) under options near the bottom you can configure the task to run if it was missed (ie the client was suspended or powered off at the scheduled time) with a suitable delay to allow boot etc.

Screen Shot 2016-04-20 at 14.41.45.png

We do this with all our front office machines, and have then schedule to run the update task at 01:00 am knowing full well most of them will be offline, but will run the task 10 mins after boot.

Providing you have the mcafee http and/or mcafee ftp repository enabled the clients will pull the DTAs directly from McAfee if your ePO server is not contactable.

Rich

4 Replies

Re: Change schedule of virusscan 8.8

Jump to solution

Hi

You can disable the Default AutoUpdate task in the VirusScan -> General Options Policy -> Display Options Policy.

Under Console Options check the 'Disable default AutoUpdate task schedule', third one down in the image below.

Screen Shot 2016-04-20 at 14.21.43.png

But don't forget to create a New McAfee Agent Update Task and assign it to the System, or you will never get updates

Regards

Richard Carpenter, CISSP

McAfee Certified Product Specialist - ePO

McAfee Volunteer Moderator

elwe31
Level 7
Report Inappropriate Content
Message 3 of 5

Re: Change schedule of virusscan 8.8

Jump to solution

Thanks you very much for your anwser.

The problem is for the Laptops clients, some clients aren't often on the network.

I want to be sure the updates run and is active.


Regards

Romain

Highlighted

Re: Change schedule of virusscan 8.8

Jump to solution

When you create the McAfee Agent Product Update Task and assign it to the Client, during the Assign Client Task configuration at the Schedule stage (Stage 2) under options near the bottom you can configure the task to run if it was missed (ie the client was suspended or powered off at the scheduled time) with a suitable delay to allow boot etc.

Screen Shot 2016-04-20 at 14.41.45.png

We do this with all our front office machines, and have then schedule to run the update task at 01:00 am knowing full well most of them will be offline, but will run the task 10 mins after boot.

Providing you have the mcafee http and/or mcafee ftp repository enabled the clients will pull the DTAs directly from McAfee if your ePO server is not contactable.

Rich

elwe31
Level 7
Report Inappropriate Content
Message 5 of 5

Re: Change schedule of virusscan 8.8

Jump to solution

Ok, I understand.

Thansk very much.

Regards

More McAfee Tools to Help You

Community Help Hub

    New to the forums or need help finding your way around the forums? There's a whole hub of community resources to help you.

  • Find Forum FAQs
  • Learn How to Earn Badges
  • Ask for Help
Go to Community Help

Join the Community

    Thousands of customers use the McAfee Community for peer-to-peer and expert product support. Enjoy these benefits with a free membership:

  • Get helpful solutions from McAfee experts.
  • Stay connected to product conversations that matter to you.
  • Participate in product groups led by McAfee employees.
Join the Community
Join the Community