Hi Heroes,
If we schedule policy based ODS to run at Sunday every week, but the computer was shutdown at Friday, will the scheduled ODS continue to run when the employee back to work next Monday? or it will not run. thanks!
Solved! Go to Solution.
There is an option in it to scan if missed. If you have that enabled, it will run when they are next online. Otherwise, no.
Thank you for posting a question.
Please find attached screenshot.
If you enabled "Run missed task" option on your ODS task, the missed ODS task will be started n minutes(you can set in the option) after started Windows on Monday.
There is an option in it to scan if missed. If you have that enabled, it will run when they are next online. Otherwise, no.
Thanks all, I will test that
Thank you for posting a question.
Please find attached screenshot.
If you enabled "Run missed task" option on your ODS task, the missed ODS task will be started n minutes(you can set in the option) after started Windows on Monday.
Corporate Headquarters
6220 America Center Drive
San Jose, CA 95002 USA